NRC ONLINE FORM, “REQUEST FOR ALTERNATIVE UNDER 10 CFR Part 50.55a(z)(1) and (2)"

ICR 202508-3150-003

OMB: 3150-0244

Federal Form Document

ICR Details
3150-0244 202508-3150-003
Received in OIRA 202112-3150-005
NRC
NRC ONLINE FORM, “REQUEST FOR ALTERNATIVE UNDER 10 CFR Part 50.55a(z)(1) and (2)"
Revision of a currently approved collection   No
Regular 08/29/2025
  Requested Previously Approved
36 Months From Approved 09/30/2025
394 297
788 1,782
0 0

10 CFR 50.55a incorporates by reference Division 1 rules of Section III, "Rules for Construction of Nuclear Power Plant Components," and Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components," of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (B&PV Code); and the rules of the ASME “Code for Operation and Maintenance of Nuclear Power Plants” (OM Code). These rules of the ASME B&PV and OM Codes set forth the requirements to which nuclear power plant components are designed, constructed, tested, repaired, and inspected. The ability of licensed facilities to comply with these requirements may be negatively impacted by the Coronavirus Disease 2019 (COVID-19) Public Health Emergency (PHE) in order to not conflict with practices recommended by the Centers for Disease Control and Prevention (CDC) to limit the spread of COVID-19 (e.g., social distancing) while performing in-service testing and inspections.To facilitate licensees’ requests for alternatives to the requirements in the above regulations, the NRC is providing an online form to submit the required information for a specific alternative request.

PL: Pub.L. 83 - 703 68 Name of Law: Atomic Energy Act of 1954
  
None

Not associated with rulemaking

  90 FR 21514 05/20/2025
90 FR 42278 08/29/2025
Yes

  Total Request Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 394 297 0 0 97 0
Annual Time Burden (Hours) 788 1,782 0 0 -994 0
Annual Cost Burden (Dollars) 0 0 0 0 0 0
No
No
External programs contributing to the progression of advanced reactor designs, causing an influx of applications for construction permits (CP), early site permits (ESP), standard design approvals (SDAs) and certifications, manufacturing license (MLs), combined licensees (COLs), for commercial nuclear power reactors, as well as operating licenses (OLs) related to the licensing processes that apply to light-water reactors (LWR) and NLWRs increased the estimated respondents by 36 and the responses by 97 for this clearance cycle. The previous enhanced form introduced excessive opportunity for error when developing the required information. The NRC staff has evaluated the electronic submission format and has determined that the previous submission format could be simplified, reducing the burden from 6 to 2 hours per submission, while still gathering the necessary information. The change in the burden per response results in a decrease in the estimated annual burden of 994 hours. The revised online form removes several fields and peer review features and simplifies the submission process. These changes are supported by feedback from the focus groups held with industry representatives under OMB Control Number 3150-0217. The following fields have been removed from the current online form in order to simplify the collection of information: Reason for Request Full Description of Proposed Alternative Description of Basis for Use Include Any Additional Information Precedents References The hourly fee rates increased from $279/hr to $317/hr for professional effort in this clearance.

$2,497,960
No
    No
    No
No
No
No
Yes
Leslie Hill 3014152158 lah1@nrc.gov

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
08/29/2025


© 2025 OMB.report | Privacy Policy